Project/Reconstruction Timeline

Date Activity
May 9, 2016 Architect RFP Advertised
July 12 and 18, 2016 Architect Interviews
August 3, 2016   Architect Recommendation to BFOC*
August 5, 2016   Principal Communication to Eastern Families
August 8, 2016 Architect Recommendation to BOE**
September 7, 2016  Principal Communication to Eastern Families
September 7, 2016  BFOC Discussion
September 13, 2016  Discussion at PTO Meeting
September 27-28, 2016 Eastern Elementary Reconstruction Visioning Session
October 5, 2016 Transition Location/Timeline Recommendation to BFOC
October 6, 2016 Principal Communication to Eastern Families
October 11, 2016  Discussion at PTO Meeting
October 17, 2016   Transition Location/Timeline Decision Made by BOE
October 21, 2016  Principal Communication to Eastern Families
December 9, 2016 Schematic Design from Architect
April 3, 2017 Transition to Bertha Vos
April–Mid-May, 2017 Abatement Work
May–June 2017 Bid Process
June 2017 Utility Disconnect
June 2017 Mobilize Construction Site
July 2017 Construction Begins
August 2018 Construction Completed
   
   *BFOC – Board Finance and Operations Committee
   ** BOE – Board of Education 

Contact Information

 

  • Jack Abate, Construction Manager
    Miller-Davis
    269.345.3561 Ext. 265
  • Christine Thomas-Hill, Executive Director of Finance and Operations 
    Traverse City Area Public Schools
    231.933.1730
  • Christine Guitar, Director of Marketing and Communications 
    Traverse City Area Public Schools
    231.933.8995
  • Biz Ruskowski, Principal 
    Eastern Elementary School 
    231.933.1662